ASIL The American Society of International Law
Home About ASIL Membership In the news Careers Resources Events
   
Search
Advanced Search
 

International Law In Brief

Developments in international law, prepared by the
Editorial Staff of International Legal Materials
The American Society of International Law
July 25, 2003



JUDICIAL AND SIMILAR PROCEEDINGS

BRIEFLY NOTED


JUDICIAL AND RELATED DOCUMENTS

International Centre for Settlement of Investment Disputes (ICSID): CMS Gas Transition Company v. Republic of Argentina, Award on Jurisdiction, Case No. ARB/01/8 (July 17, 2003)

The Tribunal held that the CMS Gas Transition Company’s claims were within its jurisdiction pursuant to the “Treaty between the United States of America and the Argentine Republic Concerning the Reciprocal Encouragement and Protection of Investment” (“BIT”) and the ICSID Convention.  

CMS Gas Transition Company (“CMS”) purchased shares of an Argentine company, Transportadora de Gas del Norte (“TGN”), pursuant to Argentina’s privatization program in 1995. Under the privatization arrangement, tariffs were to be calculated in U.S. dollars and expressed in Argentine pesos at the exchange rate at the time of billing, and were to be adjusted semi-annually under the U.S. Producer Price Index. Following Argentina’s economic and financial crisis in 1999, Argentina introduced legislation in 2001 and 2002 that restructured and renegotiated public and private contracts made in foreign currency and prevented public sector licensees such as TGN from linking tariffs to U.S. price indices, among other measures.

CMS claimed that the aggregate of these measures harmed its investment, creating a cause of action by virtue of the BIT and the ICSID Convention.

Among the number of objections to jurisdiction raised by Argentina, it challenged the admissibility of the claims by CMS on the ground that TGN was the licensee, and CMS only a minority shareholder of TGN. Argentina therefore maintained that CMS could not be considered a foreign investor for the purpose of the BIT and the ICSID Convention. In this regard, CMS argued that it was not claiming rights pertaining to TGN, but rather, as a foreign investor claiming a breach of the guarantees of legal and economic stability provided by Argentina under its privatization program.

The Tribunal held that, in view of several other ICSID decisions in addition to decisions of the International Court of Justice in this regard, there was no bar to the exercise of jurisdiction over CMS as a minority shareholder.

Argentina also maintained that the measures alleged by CMS to have harmed its investment in breach of the BIT were part of a general emergency monetary policy, and were not directly related to CMS’s investment.

The Tribunal concluded that although it was without jurisdiction to assess the legality of Argentina’s general economic policy, it did have jurisdiction “to examine whether specific measures affecting the Claimant’s investments or measures of general economic policy having a direct bearing on such investment have been adopted in violation of legally binding commitments made to the investor in treaties, legislation or contracts.”

The Tribunal therefore dismissed Argentina’s objections and upheld jurisdiction over the dispute.

Members of the Tribunal

Professor Francisco Orrego Vicuña, President

The Honorable Marc Lalonde P.C., O.C., Q.C.

H.E. Judge Francisco Rezek

Click here for the award.

Back to top

German Supreme Court: Distomo Massacre Case, BGH - III ZR 245/98 (June 26, 2003)

The German Supreme Court (“the Court”) held that Germany was not liable to Greek plaintiffs for reparation payments in relation to the massacre in the village of Distomo, Greece, caused by SS-troops, which were integrated into the German Wehrmacht, in 1944.

The plaintiffs, whose parents were killed in the massacre that constituted revenge for partisan activities, had brought an action for a declaratory judgment that Germany was liable for reparation. The courts of first and second instance dismissed the action. Besides the proceedings initiated in Germany, the plaintiffs also participated in a claim for damages for the Distomo incident brought in the Court in Livadeia, Greece. On October 30, 1997, the Greek court rendered a judgment in default against Germany and awarded damages. The judgment, however, could not be enforced in Greece because the Greek government refused to give its permission necessary under Greek law.

The Court held that it could not give recognition to the default judgment that was rendered against Germany by the Court in Livadeia. The Court found that the judgment could be recognized neither on the basis of a 1961 bilateral agreement concerning enforcement and recognition of judgments (Vertrag zwischen der Bundesrepublik Deutschland und dem Königreich Griechenland über die gegenseitige Anerkennung und Volstreckung von gerichtlichen Entscheidungen, Vergleichen und öffentlichen Urkunden in Zivil- und Handelssachen vom 4. November 1961), nor on the basis of Section 328 of the German Code of Civil Procedure, for both required that, as a precondition, Greece had jurisdiction. The Court found that Greece lacked jurisdiction over Germany because the acts at issue were sovereign or public acts (“acta iure imperii”) for which, according to a fundamental principle of international law, Germany was immune from another State’s jurisdiction.

The Court found, however, that, in general, Germany could be liable as the legal successor of the German Reich for compensation claims against the latter. It noted in this context that the so-called “Two-plus-Four” Agreement of September 12, 1990, constituted a final settlement of reparations as required under Article 5 paragraph 2 of the 1953 London Debt Agreement to lift the moratorium it imposed on the judicial consideration of reparation claims of (1) states that were at war with Germany, (2) states that were occupied by Germany or (3) citizens of those states. The court found that the “Two-plus-Four” Agreement as a settlement of reparation claims did not preclude judicial consideration of individual claims, for, besides the fact that Greece was not even a party to this treaty, there was no reason to assume that Greece at any point waived the right of its citizens to bring individual claims against Germany. The court further found that the 1960 bilateral agreement on reparation payments in favor of Greek citizens who endured Nazi prosecution (Vertrag vom 18. März 1960 zwischen der Bundesrepublik Deutschland und dem Königreich Griechenland über Leistungen zugunsten griechischer Staatsangehöriger, die von nationalsozialistischen Verfolgungsmaßnahmen betroffen sind), on the basis of which Germany had already made a payment of 115 million German Marks to Greece, did not preclude legal claims by individual citizens.

In regard to applicable law, the Court noted that since Germany was liable only for claims against the German Reich, it had to take into consideration the state of international and national law as of 1944. The court therefore found that plaintiffs had no cause of action under international law for damage resulting from a State’s violation of the laws of war, for international law as of 1944 did not provide individuals with a cause of action but conferred upon States the right to diplomatic protection. Thus, the court further noted that only States, in asserting their own right to ensure in the person of its nationals respect for the rules of international law, could demand reparation from other States for violations of international law. The Court found that, regarding violations of the laws of war, this approach is confirmed by Article 2 of the 1907 Hague Convention Respecting the Laws and Customs of War on Land, which expressly provided that its provision apply between parties only.

The Court furthermore held that there was no legal basis for the plaintiffs’ claim under German law. The plaintiffs had argued that Germany would be liable on the basis of Section 839 paragraph 1 of the Civil Law Code in connection with Article 131 of the Weimar Constitution for harm caused by official acts. The Court found that even though the massacre in Distomo fulfilled all elements of Section 839 paragraph 1, the provision was not meant to provide a cause of action for reparation to foreign citizens that were harmed by conduct of German troops in violation of the laws of war.

Click here for the decision. (in German)

Back to top

Eritrea-Ethiopia Claims Commission (EECC): Partial Awards on Prisoners of War between the State of Eritrea and the Federal Democratic Republic of Ethiopia: Ethiopia’s Claim 4; Eritrea’s Claim 17 (July 1, 2003)

The Eritrea-Ethiopia Claims Commission (“EECC” or “Commission”) issued two awards addressing both Eritrea and Ethiopia’s claims regarding the mistreatment of prisoners of war (“POWs”) following the outbreak of hostilities in May 1998. The Commission’s mandate, set forth in Article 5, paragraph one of the Agreement between the Government of the Federal Democratic Republic of Ethiopia and the Government of the State of Eritrea of December 12, 2000 (“the Agreement”) provides, inter alia, that the Commission is to decide through binding arbitration all claims for loss, damage, or injury by one Government against the other and by nationals of one party against the Government of the other Party that are related to “violations of international humanitarian law, including the 1949 Geneva Conventions, or other violations of international law.” (See 40 ILM 260 (2001)).

The commission generally found that both Eritrea and Ethiopia (“the Parties”) were committed to the most fundamental principles of international law bearing on POWs, as evidenced by the organized military training programs each Party conducted for the treatment of POWs. Nonetheless, the Commission found that “[t]here were deficiencies of performance on both sides, sometimes significant, sometimes grave.”

In terms of the scope of the Commission’s jurisdiction, Ethiopia argued that Article 5, paragraph one of the Agreement did not grant the Commission jurisdiction over claims concerning the treatment of POWs, including claims for repatriation, arising after December 12, 2000. The Commission found that its jurisdiction extended to claims by either party based upon alleged delays in repatriation of POWs. However, the Commission found that it lacked jurisdiction over other claims not filed before December 12, 2001.

In regard to applicable law, the Commission observed that Eritrea was not a party to the 1949 Geneva Conventions prior to its accession to the Conventions on August 14, 2000. Further, the Commission noted that Eritrea’s non-acceptance of the Conventions was evidenced by its refusal to grant access to the International Committee of the Red Cross (“ICRC”) to visit Ethiopian POWs. The Commission held that as a consequence of Eritrea’s non-acceptance of the Geneva Conventions until August 2000, the law applicable to the armed conflict between Eritrea and Ethiopia until August 2000 was customary international law, including customary international humanitarian law, as exemplified by the relevant sections of the four Geneva Conventions of 1949 and in particular the Geneva Convention Relative to the Treatment of Prisoners of War (“Geneva Convention III”), frequently invoked by both Parties in support of their claims. The Commission noted that there was nearly universal acceptance of the Geneva Conventions and significant authority for the proposition that the 1949 Geneva Conventions have largely become expressions of customary international humanitarian law. It concluded that if either Party wished to assert that a particular relevant provision of the Geneva Conventions could not be applied as evidence of customary international law, the burden of proof would fall on the asserting party to prove its non-applicability as customary international law.

In terms of the evidentiary standard of proof, the Commission required clear and convincing evidence of violations of international law in order to establish liability. Further, the Commission found that “[t]he consistent and cumulative character of much of the Parties’ evidence was of significant value to the Commission in making its factual judgments.”

Ethiopia’s Claim 4: The Commission found that Eritrea’s refusal, from May 1998 to August 2000, to allow the ICRC access to Ethiopian POWs, to register POWs, to interview them without witnesses, and to provide them with the customary and services, resulted in a violation of customary international law. The Commission disagreed with Eritrea’s argument that the provisions of the Geneva Convention III requiring external scrutiny of the treatment of POWs and access to the ICRC were merely implementing procedural provisions and not constituting part of customary international law. The Commission noted that these requirements “incorporate past practices that had standing of their own in customary law, and [...] are of such importance for the prospects of compliance with the law that it would be irresponsible for the Commission to consider them inapplicable as customary international law.”

The Commission further found that Eritrea was liable under customary international law for the following acts: beating and frequently killing Ethiopians upon capture and its immediate aftermath; depriving Ethiopian POWs of footwear during long walks; allowing its interrogators to threaten or beat Ethiopian POWs; confiscating personal property of Ethiopian POWs; permitting pervasive and continuous physical and mental abuse in its camps from May 1998 to August 2002; seriously endangering the health of Ethiopian POWs at Embakala, Digdigta, Afabet and Nakfa camps; failing to provide sanitary housing, bath and food facilities; failing to provide the standard of medical care required for Ethiopian POWs; failing to provide for required preventive care by segregating Ethiopian POWs with infectious diseases; subjecting Ethiopian POWs to unlawful conditions of labor; permitting unnecessary suffering of Ethiopian POWs during transfer between camps; failing to allow Ethiopian POWs to seek redress and punishing those who did. 

Eritrea’s Claim 17: The Commission found Ethiopia liable for the following violations of customary international law: failing to take effective measures to prevent incidents of beatings and abuse of Eritrean POWs; depriving Eritrean POWs of footwear during long walks; failing to protect personal property of Eritrean POWs, subjecting Eritrean POWs to enforced indoctrination; permitting health conditions at Mai Kenetal to endanger the health of Eritrean POWs; failing to provide an adequate diet to Eritrean POWs; failing to provide proper medical care and preventive care; and delaying the repatriation of 1,287 Eritrean POWs in 2002 for seventy-seven days longer than was reasonably required.

In regard to Eritrea’s claim for the alleged unlawful assault of female POWs, the Commission found that Eritrea failed to submit sufficient evidence documenting sexual assault of female POWs, and while noting the vulnerability of female POWs and the significance of Eritrea’s claim, held that it could not lower the standard of evidence in this regard.

Members of the Eritrea-Ethiopia Claims Commission:

Hans van Houtte, President

George H. Aldrich

John R. Crook

James Paul

Lucy Reed

Click here for the awards.

Back to top

European Court of Human Rights (ECHR): Case of Murphy v. Ireland (Application no. 44179/98) (July 10, 2003)

The ECHR held that Ireland was not in violation of Article 10 of the Convention for the Protection of Human Rights and Fundamental Freedoms (the “Convention”).

The case was originally brought against Ireland before the European Commission of Human Rights, and was transferred to the ECHR on November 1, 1998, when Protocol No. 11 of the Convention came into force.  The applicant claimed that the prohibition of the broadcast of his religious advertisement by virtue of Ireland’s 1998 Radio and Television Act constituted a violation of his rights under Articles 9 and 10 of the Convention. In particular, the applicant claimed that his advertisement was protected under Article 10 of the Convention which extended to ideas that “offend, shock or disturb” in accordance with

Handyside v. the United Kingdom (December 7, 1976).

The ECHR found that the issue did not concern a restriction of the freedom to manifest one’s religion under Article 9 of the Convention, but rather, a restriction of the right to freedom of expression under Article 10. The ECHR noted that Article 10 protected not only the content and substance of the information, but also the means of dissemination, given that any restriction on the means necessarily interfered with the right to receive and impart information.

The ECHR found that since the prohibition related only to advertising, such limitation reflected a reasonable distinction made by the State, particularly in view of the partisan nature of advertisement. The ECHR noted that there appeared to be no consensus between the Contracting States of the ECHR as to the limits of regulating religious advertisements, and that a wide margin of appreciation was generally accorded to ECHR Contracting States in regulating these matters.

The Court found that the Government of Ireland’s objective to ensure respect for religious doctrines and beliefs for public order and safety were legitimate aims for the purposes of Article 10 §2 of the Convention.

Click here for the decision.

Back to top

UNCLOS Arbitral Tribunal: Ireland v. United Kingdom (Order No. 3 - Suspension of Proceedings on Jurisdiction and Merits and Request for Further Provisional Measures) (June 24, 2003)

The Arbitral Tribunal (“the Tribunal”) decided unanimously that further proceedings on jurisdiction and merits would be suspended until no later than December 1, 2003. In addition, it affirmed a provisional measure on co-operation prescribed by the International Tribunal for the Law of the Sea (“ITLOS”) in its Order of December 3, 2001 (see ILIB summary of February 11, 2002) and rejected Ireland’s request for additional provisional measures.

The case concerns a dispute between Ireland and the United Kingdom under the 1982 United Nations Convention on the Law of the Sea (“the Convention”) over discharges into the Irish Sea of certain radioactive wastes produced by or as a result of the operation of a mixed oxide (“MOX”) fuel plant at Sellafield in the United Kingdom. The MOX plant reprocesses spent nuclear fuel into a new, mixed oxide fuel. Ireland asserted that in respect of the establishment and prospective operation of the MOX plant, there was a risk of harm arising from (1) the discharge of radioactive waste, (2) the transport of radioactive material through the Irish Sea, and (3) the storage of such material in the facility. Ireland further argued that under the Convention the United Kingdom has obligations concerning the protection of the maritime environment, the prevention and control of pollution and co-operation between States. Ireland alleged that the United Kingdom was in breach of several of its obligations under the Convention and referred in particular to Articles 123, 192, 193, 194, 206, 207, 211, and 213.

The procedural background to this case began on October 25, 2001, when Ireland submitted to the United Kingdom a Notification and Statement of Claim instituting arbitral proceedings as provided for in Annex VII to the Convention. Ireland also submitted a request for provisional measures pending the constitution of the Tribunal. Article 290 paragraph 5 of the Convention provides that “pending the constitution of an arbitral tribunal to which a dispute is being submitted under this section [...] the International Tribunal for the Law of the Sea [...] may prescribe, modify or revoke provisional measures in accordance with this article if it considers that prima facie the tribunal which is to be constituted would have jurisdiction and that the urgency of the situation so requires.” Thus, ITLOS, finding that the Tribunal to be constituted under Annex VII has prima facie jurisdiction, prescribed provisional measures on December 3, 2001. The Tribunal was subsequently established in February 2002.

In observing whether it had jurisdiction not only prima facie but also in a definitive sense, the Tribunal had to consider two categories of objections raised by the United Kingdom. The first category of objections to jurisdiction and admissibility concerned the Convention itself and other instruments invoked by Ireland such as the 1992 Convention for the Protection of the Marine Environment of the North-East Atlantic (“the OSPAR Convention”). The Tribunal, however, rejected the United Kingdom’s objections in this respect, finding, inter alia, that the OSPAR Convention did not cover the field as to invoke Articles 281 or 282 of the Convention which would have precluded the Tribunal’s jurisdiction. The second category of the United Kingdom’s objections concerned certain European Community law issues. As to the second category of the United Kingdom’s objections, the Tribunal found that it is not clear whether “the provision of the Convention on which Ireland relies are matters in relation to which competence has been transferred to the European Community and, indeed, whether the exclusive jurisdiction of the European Court of Justice, with regard to Ireland and the United Kingdom as Member States of the European Community, extends to the interpretation and application as such and in its entirety.” The Tribunal held that if this were the case, the jurisdiction of the Tribunal would be precluded by Article 282 of the Convention. The Tribunal recognized that these matters have to be determined within the institutional framework of the European Communities and therefore held that until these issues are definitely resolved, it could not firmly establish jurisdiction in respect of all or any of the claims of the dispute.

As to the additional provisional measures requested by Ireland, the Tribunal found that its competence to prescribe such measures was contained in Article 290 of the Convention. Ireland argued that (1) discharges from the MOX plant constitute serious harm to the environment and irreparable prejudice to Ireland’s claimed right that the Sea not be polluted, (2) the United Kingdom’s failure to consult and co-operate with Ireland constitutes irreparable prejudice to Ireland’s claimed right to such consultation and co-operation, and that (3) it has a right to require the United Kingdom to undertake a proper environmental assessment, in accordance with Article 206 of the Convention. The United Kingdom argued that the discharges would not cause a serious threat, that it complied with the ITLOS Order of December 3, 2001 and that compliance with some of the additional measures sought would mean closing down the MOX plant for several months, which could eventually cause serious prejudice to the United Kingdom.

As to Ireland’s first claim, the Tribunal held that the harm caused by discharges was not “serious” and thus did not meet the threshold test in Article 290 paragraph 1. It further found that “there is no urgent and serious risk of irreparable harm to Ireland’s claimed rights, which would justify the tribunal in prescribing provisional measures relating to discharges form the MOX plant. As related to Ireland’s second point of request, the Tribunal found that no further order was required as to co-operation and the provision of information at this stage. As to Ireland’s claim in respect to the environmental assessment, the Tribunal held that this was a key question on the merits and that Ireland’s request “would not give any clear guidance to the United Kingdom of what conduct is required of it pending a final decision.”

The Tribunal however, affirmed the provisional measure on co-operation prescribed by ITLOS in its Order of December 3, 2001 and requested the parties to “take such steps as are open to them separately or jointly to expedite the resolution of the outstanding questions of European Community law.”   

Members of the Tribunal

Judge Thomas A. Mensah, President

Professor James Crawford SC

Maître. L. Yves Fortier CC QC

Professor Gerhard Hafner

Sir Arthur Watts KCMG QC

Click here for the decision.

Back to top

OSPAR Arbitral Tribunal: Ireland v. United Kingdom, Dispute Concerning Access to Information Under Article 9 of the OSPAR Convention (July 2, 2003)

The Tribunal in its final award found by majority decision that Ireland’s claim for information did not fall within Article 9(2) of the 1992 Convention for the Protection of the Marine Environment of the North-East Atlantic (“the OSPAR Convention”).

The dispute was the first one under the OSPAR Convention and concerned the access to information about a mixed oxide (“MOX”) fuel plant at Sellafield in the United Kingdom. Ireland claimed that the United Kingdom had breached its obligations under Article 9 of the OSPAR Convention by refusing to disclose information redacted from two reports prepared as part of the approval process for the MOX plant. The United Kingdom argued that the information was deleted for reasons of commercial confidentiality.

The relevant sections of Article 9 of the OSPAR Convention read:

9.1. The Contracting Parties shall ensure that their competent authorities are required to make available the information described in paragraph 2 of this Article to any natural or legal person, in response to any reasonable request, without that person’s having to prove an interest, without unreasonable charges, as soon as possible and at the latest within two month.

9.2. The information referred to in paragraph 1 of this Article is any available information in written, visual, aural or data base form on the state of the maritime area, on activities or measures adversely affecting or likely to affect it and on activities or measures introduced in accordance with the Convention.                             

9.3. The provision of this Article shall not affect the right of Contracting Parties, in accordance with their national legal systems and applicable international regulations, to provide for a request for such information to be refused where it affects:

                                    ...

            (d) commercial and industrial confidentiality

According to the parties’ final submissions it appeared to the Tribunal, which was established pursuant to Article 32 of the OSPAR Convention, that it had to determine three questions: (1) whether Article 9(1) of the OSPAR Convention required a Party to disclose or to set up a procedure to disclose “information” within the meaning of Article 9(2), (2) whether the material Ireland wanted to be disclosed constitute “information” for the purpose of Article 9(2), and, (3) whether the United Kingdom thus withheld information contrary to Article 9(3).

As to the applicable law, the Tribunal had to decide, inter alia, whether the reference of “applicable international regulations” in Article 9(3) of the OSPAR Convention would include, as contended by Ireland, also the 1998 Aarhus Convention on Access to Information, Public Participation in Decision-making and Access to Justice in Environmental Matters (“the Aarhus Convention”) which neither Ireland nor the United Kingdom had ratified. By a majority comprising Professor Michael Reisman and Lord Mustill, the Tribunal found that it could only consider current international law and practice insofar as such law and practice are admissible under Article 31 of the Vienna Convention and held that it could not apply the Aarhus Convention.

In relation to the first question before the Tribunal, the United Kingdom argued that Article 9(1) of the OSPAR Convention did not establish a direct right to receive information but rather required Parties to establish a domestic framework for the disclosure of information. The United Kingdom asserted that thus, Ireland only had a cause of action for breach of Article 9 if the United Kingdom had failed to provide a regulatory framework for disclosure of information. The United Kingdom maintained that it had taken the required legislative and administrative measures.

The Tribunal rejected the United Kingdom’s arguments and found by majority composed of Lord Mustill and Dr. Griffith QC that “upon its proper construction Article 9(1) requires an outcome of result, namely that information falling within the meaning or Article 9(2) (and not excluded under Article 9(3)) is in fact disclosed in conformity with the Article 9 obligation imposed upon each Contracting Party.”

As to the second question, the United Kingdom asserted that the information requested by Ireland does not fall under Article 9(2). The Tribunal rejected by a majority comprising Lord Mustill and Professor Reisman Ireland’s argument for a broad interpretation of Article 9(2) and held that information to fall under 9(2) has to be related to the state of the maritime area, and, focusing on the second of the three categories of Article 9(2), further held that such information has to be on activities and measures “adversely affecting or likely to affect” the maritime area. If found that Ireland had failed to demonstrate that the 14 categories of information which were redacted from the reports and which it desired to obtain were “information on the state of the maritime area” or on “activities and measures adversely affecting or likely to affect it.”

Concluding that the information sought by Ireland did not fall within Article 9(2), the Tribunal found there was no need to consider the third question.

In a short declaration Prof. Reisman explained that he did not join the majority in their decision on Article 9(1) because in his opinion, “Article 9(1) is not expressed in terms to establish an obligation on the international plane to provide information, with the performance of that obligation in specific cases to be subject to the jurisdiction of a Tribunal established under Article 32.”

In a dissenting opinion Dr. Griffith QC disagreed as to the majority’s decision regarding the applicable law, concluding that the Aarhus Convention fell within the definition of applicable law and Article 31 of the Vienna Convention. In addition, he disagreed with the majority’s narrow interpretation of the second category of information under Article 9(2) and the majority’s conclusion that the onus of proof to establish that the MOX fuel production is an activity “adversely affecting or likely to affect” the maritime area was on Ireland.

Members of the Tribunal

Professor W. Michael Reisman, Chairman

Dr. Gavan Griffith QC

Lord Mustill

Click here for the decision.

Back to top

World Trade Organization (WTO) (Final Panel Report): United States-Definitive Safeguard Measures on Imports of Certain Steel Products WT/DS248/R-WT/DS259/R (July 11, 2003)

The WTO Panel concluded that the safeguard measures imposed by the United States on the imports of certain steel products were inconsistent with the provisions of the GATT 1994 and the Agreement on Safeguards, which provide WTO members with a conditional right to limit market access and to take measures otherwise inconsistent with its obligations under the GATT in order to obtain temporary relief when unforeseen developments have resulted in increased imports that are causing or threatening to cause serious injury to the relevant domestic producers. The complainants challenging the measures were Brazil, China, the European Communities, Japan, Korea, New Zealand, Norway and Switzerland. 

The complainants challenged the application of safeguard measures pursuant to the U.S. President’s Proclamation No. 7529 of March 5, 2002 entitled “To facilitate Positive Adjustment to Competition from Imports of Certain Steel Products” in which the U.S. imposed a tariff of 30% on imports of Plate, Hot-Rolled Steel, Cold-Rolled Steel, and Coated Steel. The complainants challenged the application of the safeguard measures imposed by the United States in addition to the methodologies of the United States International Trade Commission (“USITC”) in its determination of safeguard measures pursuant to Proclamation No. 7529.

The Panel noted that safeguard measures under Article XIX:1(a) of GATT 1994, as interpreted by the WTO Appellate Body in Argentina-Footwear (EC), were intended by the drafters of the GATT to be “matters out of the ordinary” and in short, “emergency actions.” The Panel observed that such actions may be taken when a WTO Member faces developments that were unforeseen when the Member incurred its GATT 1994 obligations.                                                                           

In respect of the unforeseen development determination, the United States argued that the Russian financial crisis, the Asian financial crisis, the continued strength of the U.S. market, along with the persistent appreciation of the U.S. dollar constituted a combination of unforeseen developments. The European Communities, China, Switzerland and Norway argued that no combination of the above-mentioned events cited by the USITC could constitute an unforeseen development.

The Panel found that the report on unforeseen developments submitted by the USITC, although describing a “plausible set of unforeseen developments that may have resulted in increased imports to the United States from various sources, [...] falls short of demonstrating that such developments actually resulted in increased imports into the United States causing serious injury to the relevant domestic markets.” The Panel found that the USITC report “failed to link the steel market displacements to the specific increased imports into the United States at issue.” The Panel therefore found that the failure to provide a reasoned and adequate explanation demonstrating that such unforeseen developments resulted in increased imports and serious injury to the relevant domestic producers was inconsistent with, inter alia, Article XIX:1 of GATT 1994 and Articles 2.1 and 3.1 of the Agreement on Safeguards. The Panel recommended that the Dispute Settlement Body of the WTO request the United States to bring its safeguard measures in conformity with its obligations under the Agreement on Safeguards and GATT 1994.

Click here for the decision.

Back to top


BRIEFLY NOTED

European Union (EU): Council adopted proposals on GMOs (July 22, 2003)

On July 22, 2003, the Council of Ministers formally adopted two European Commission proposals for regulations on genetically modified organisms (GMOs). The two proposals were previously adopted by the European Parliament on July 2, 2003.

This new legislation will establish a coherent system of authorization, labeling and tracing of food and feed products derived from GMOs. Authorization will be granted on the basis of a single risk assessment conducted by the European Food Safety Authority (“EFSA”) and will be based on the “one door - one key” principle, which means that authorization can only be received either for none or for both, deliberate release into the environment and use of the GMO in food and/or feed. The labeling requirements will apply to all foods consisting of, containing or produced from GMOs irrespective of whether there is DNA or protein of GM origin in the final product and all genetically modified feed. The traceability requirements will require business operators to transmit and retain information that helps to track the movement of GM products throughout the production and distribution chain.

The new legislation will enter into force 20 days after its publication in the Official Journal of the European Union.

Click here and here for the proposals.

Back to top

European Union (EU): Council adopted Directive on greenhouse gas emissions trading (July 2, 2003)

On July 22, 2003 the Council adopted a Directive creating a scheme for greenhouse gas emission allowance trading within the European Community. Previously, the European Parliament voted in favor of the Directive on July 2, 2003. The Directive aims to promote the reduction of greenhouse gas emissions in a cost-effective manner. The scheme covers all greenhouse gases covered by the Kyoto Protocol but only the carbon dioxide emissions from the activities listed in Annex I of the Directive will be included from the start. The first period of the trading scheme will start on January 1, 2005.

Click here for the proposal.

Back to top


International Law In Brief (ILIB) - Copyright 2003 - The American Society of International Law (ASIL)
Editors: Ruth Teitelbaum, Elisabeth Handl, Scott Smith
- ILIB is a free-of-charge electronic resource.  In order to sign up to receive ILIB, or to unsubscribe, please follow instructions at http://web3.ags.com:81/guest/RemoteListSummary/ILIB
- Shortly after it is distributed over the ILIB list serve, each ILIB issue is also available at the main ILIB web page at http://www.asil.org/ilibindx.htm, or ILIB Archive at http://www.asil.org/ilib/ilibarch.htm.  If you have any problems using web links contained in ILIB, please consider using ILIB copies posted on one of the previous web pages.  Please note that web links contained in ILIB are accurate as of the date of publication of each ILIB issue, and we are not responsible for their accuracy thereafter.
- Information on subscription procedure and rates for International Legal Materials (ILM) are available at http://www.asil.org/internati.htm
- For a working list of Internet resources assembled and used by the ILM Office in compiling both ILM and ILIB, please visit http://www.asil.org/ilmlinks.htm
- In order to sign up to receive ASIL Insights, please follow instructions at http://www.asil.org/insights.htm
- For ASIL membership information, visit us on the Internet at http://www.asil.org/member.htm
- To comment on this publication, send an e-mail message to the ILM Managing Editor at rteitelbaum@asil.org

 

 

 
 
Contact Us Site Map Privacy